Construction Updates

Fire-EMS Fire House No. 1 
March 2018 Update:

  • Mock-up walls are being constructed in front of the trailer.
  • Sanitary sewer connection has been made to the manhole on the south side of Davis Blvd./Dove Road intersection.  Vaquero HOA is aware the town will be replacing the sod and one tree that was removed for the sewer connection.
  • Site walls are progressing with the completion of the footings for the wall next to the building. 
  • Utilities under slab have recently been completed and the pad has been put back to grade.
  • Electrical transformer and wiring are presently being placed for permanent power to be energized later this week.
  • The four bays and living quarters slab was poured on Friday, March 23, 2018
  • The slab for the administration building is scheduled to be poured April 3, 2018.
  • Masons to mobilize week of April 1, 2018, to start the CMU exterior walls.
  • Structural steel is scheduled to be delivered the second week of April.

Aerial Photo 1

3.28

Aerial Photo 2

3.28 A

Construction Progress on April 10th, 2018